|
The second London WRG visit to
the Lichfield Canal this year saw the first ever joint dig with a newly
reconstituted North-East WRG. With a long list of tasks and a large number
of willing volunteers it promised to be an excellent dig.
Saturday morning. The advance guard reach site to find that the local
groups JCB had developed a leak in its hydraulics and could not be moved.
While this was being repaired the first job was to finish off the
shuttering for the back filling of the swing bridge. At some point while
this work was being done the brick delivery truck got bogged down on the
access road and all the bricks had to be off loaded before the concrete
delivery arrived! At around this point the brick laying team started on
the bridge hole wing walls and the concrete lorry arrived, found it could
not get on site so concrete had to be picked up in the dumpers and then
shoveled round the shuttering on the bridge. An hour and a half later ~4
cubic metres of concrete had been poured, vibrated down and emergency
repairs had been made to the offside shuttering as it was bulging out due
to the weight of concrete. After the rushing around was over and everyone
had had a brew a group was started on exposing the culvert fitted by last
years canal camp so that it could be piled round and not through. Another
team built the scaffolding tower to be used for piling and John Park was
setting new records for speed brick laying.
Saturday afternoon. The piling team started off slowly with the
(relatively) easy job off leveling off some previously placed piles, so
while Angus struggled with the beast of Lichfield (its that JCB again) the
rest of my motley team got to play with a compressor and a piling hammer.
While a lot of noise was being made half way down the cut yet more brick
laying was being done, trees were being felled and the exposure of the
culvert had shown that it leaks. As the sun set the piling team forgoes
the bus home and carries on working, the job being removing some short
piles so that long piles could replace them. After much discussing of
various methods of removing the piles the job was finally done just as the
light finally went completely.
Saturday evening. Returned to hall to find the children's disco still
in full swing and dinner would be delayed. Found that even ear defenders
cannot prevent you hearing the Barbie Song but in the end it all finished.
Dinner was up to its usual standards and the weary navvies adjourned to
the pub for a couple of pints of mild.
Sunday morning. Arrived on site to find a large crane had appeared to
help mount the superstructure of the swing bridge, this task took most of
the rest of the day and the bridge was later tested with the weight of
about twenty navvies later on. The brick laying team started off again,
the name tags were attached to piles, ground anchors were fitted and the
piling team had the enjoyable task of refitting the piles removed the day
before. This developed into a quite hairy task, as getting the last pile
to slot into the two next to it required the use of the piling hammer at
above head height and involved Matt and I standing on top of the piles
already placed to pound this one in. Well in the end the task was
completed and we had managed to straighten out the run of piles, not bad
for a team with practically no piling experience!
Sunday afternoon. The work carried on, the piling team moved to the
bridge and fitted a few more piles before calling it a day, the crane
finished its work, mince pies were delivered and the JCB sprung a leak
again.
Special thanks to Matt and Helen (Bushbaby) for organising a brilliant
weekend, despite some minor set backs I believe that everyone had an
enjoyable dig.
|