London WRG: Basingstoke
Dig: 23-24 February 2002 Report
by Ed Walker
A relatively large
number of London WRG'ies hit the "Bleak House" pub on the Friday
night to find that the closest approximation to real ale was still
Guinness. Meeting up with Pete Redway we found out that the main job for
the weekend was putting in more back pump pipe sections and tarting up
Lock 11.
On site the next day, a team lead by Moose and Maria started work on
pouring some more concrete around the outlet weir to strengthen the
structure, the only problem being that all the mud had to be dug out
first. Sometime latter success was declared by a number of mud splattered
navvies and the pour started.
At the other end of the lock, progress was slower. The excavator supplied
for the pipe laying job had come with too large a digging bucket and a
four foot deep trench had to be hand dug between the concrete around the
bywash pipe and the fibre optic conduit. Much hand digging later and the
previous pipe section was found but offering up the next section showed up
another problem, the concrete around the bywash would have to be trimmed
back. It now being quite late we decided to put that off to the next day.
In the middle of site the rest of the group including Alex (a new
volunteer) did some landscaping and started to re-lay the towpath.
Crawling back to Woodham Church Hall that night we were treated to a
chicken stew courtesy of Lesley and Maria and headed off to "The
Plough" in Byfleet for a couple of pints of "flat cap" and
"squashed rat and warthog", thanks to Daryl for driving us to
the pub and for recovering Martin after the ResCom meeting.
The next day on site was wetter than the first, with the concreteing
finished the landscpaing was accelerated and by the end of the day a nice
towpath ran the length of the lock. Back down the trench the application
of Dave Miller, Martin and a Kango soon dealt with the obstructing
concrete and the first pipe section was connected up, leveled out using a
laser level and filled in again. Another section of pipe was then emplaced
and and a temporary towpath surface poured.
All in all, a constructive dig with a lot of useful work done, we would
have got a lot more pipe laid though if we hadn't had so much trouble with
the fibre optic conduit!
Ed Walker
Return to London WRG page
Page written and maintained by Dan
Evans (dan at danevans.co.uk).
Originally written: 27 January 2002. Last
update: 27 January 2002.
|